Decided

No. 19-623

Shrinivas Sugandhalaya LLP v. Balkrishna Setty, et al.

from the United States Court of Appeals for the Ninth Circuit

See other cases from the Ninth Circuit.

Docket Entries

JUDGMENT ISSUED.

Petition GRANTED. Judgment VACATED and case REMANDED for further consideration in light of GE Energy Power Conversion France SAS v. Outokumpu Stainless USA, LLC, 590 U. S. ___ (2020).

DISTRIBUTED for Conference of 6/4/2020.

Motion to extend the time to file a response is granted and the time is extended to and including December 23, 2019.

Motion to extend the time to file a response from December 16, 2019 to December 23, 2019, submitted to The Clerk.

Petition for a writ of certiorari filed. (Response due December 16, 2019)

Parties

Shrinivas Sugandhalaya LLP, Petitioner, represented by Brian William Esler

Balkrishna Setty and Sugandhalaya LLP, Respondent, represented by Scott S. Brown

 
Last updated: April 26, 2024